Bringing the benefits of solar power to middle and lower income residents of Dallas, Texas
(This is the Executive Summary for a new project we’ve been working on for the past year, Patriot Solar Power. It was originally inspired by T. Boone Pickens and the Pickens Plan. We think we’ve finally got the details worked out well enough to see if there is interest in funding a pilot program, but the ultimate goal is to bring a greener Dallas to all our residents, regardless of income).
Project Overview:
Photovoltaic generation of power (solar power) has become an economically viable source of power generation in Dallas, Texas because of incentives at the federal level with the 30% renewable energy credit and locally with Oncor’s new incentive of $2.46 per watt of photovoltaic power for residential users (limited to five kilowatts per customer). However, the initial capital cost of installing a solar power system (estimated by Oncor at $6,000 to $10,000 per kilowatt) is prohibitive to almost all middle-income and lower-income residents in Dallas.
Central Dallas Community Development Corporation (Central Dallas CDC) wants to change this and bring the benefits of solar power to the middle and lower income residents of Dallas. We will do this acting through a limited liability company, Patriot Solar Power, L.L.C. Patriot Solar Power, L.L.C. will make solar power available to residents living in areas of the City of Dallas where the average median income is less than 80% of that for the Dallas Metropolitan Statistical Area, beginning with an initial program bringing solar power to 100 households.
The solar systems will be installed for program participants at no cost. Patriot Power will receive as lease payments a portion of the utility bills paid by participants to their electric company, based on the value of the electricity produced by the solar systems. The process will be entirely transparent to residents, who will pay their utilities bills as always. The utility bills of the residents will not increase because of the solar power systems. In addition, Patriot Power, L.L.C. will return a yearly rebate to each participant equal to 10% of the value of the energy generated from the solar panels at their home.
Project Financing – New Markets Tax Credits:
The economics of Patriot Power, L.L.C. work because the existing incentives for solar power can be wrapped within a New Markets Tax Credit structure, potentially reducing the cost by an additional 25%. New Markets Tax Credits must remain invested in the project for a seven-year period. By the end of the period, a sinking fund established to repay the New Markets Tax Credit loan that will have grown sufficiently to refinance the loan.
At the end of the seven-year period, Patriot Power, L.L.C. will double the rebate to program participants to 20% of the value of the electricity produced by the solar system. Any excess proceeds beyond those needed to maintain and operate the solar system will be expended to pay for the installation of additional solar systems or for other activities that will result in the reduction of the use of nonrenewable energy resources in North Central Texas.
Showing posts sorted by relevance for query Patriot Power. Sort by date Show all posts
Showing posts sorted by relevance for query Patriot Power. Sort by date Show all posts
Sunday, July 5, 2009
Monday, August 31, 2009
What we do with our time at Central Dallas CDC
Last week I took a short break from my refusal to manage and we all recorded how we spent our time during the week. So far I have only compiled the information for the 3.5 employees (including myself) that we have at Central Dallas CDC, not our various contract workers, but I’m already finding some interesting things.
First, Central Dallas CDC officially works on a 37.5 hour week, so if everybody worked the required hours and no more, that would be just over 130 hours total per week. The actual total last week was 175 hours—so we worked more than enough hours to justify another full time employee (no worries about overtime, we are all exempt employees). I believe in hard work, probably more strongly than you can imagine, but too many fifty hour weeks (for years on end now) can wear on people. That’s especially true because I think the actual hours worked were higher than those recorded. Just reading through the time sheets I noted that a number of tasks I know were done during the week were never recorded.
Here’s how we spent our time:
First, Central Dallas CDC officially works on a 37.5 hour week, so if everybody worked the required hours and no more, that would be just over 130 hours total per week. The actual total last week was 175 hours—so we worked more than enough hours to justify another full time employee (no worries about overtime, we are all exempt employees). I believe in hard work, probably more strongly than you can imagine, but too many fifty hour weeks (for years on end now) can wear on people. That’s especially true because I think the actual hours worked were higher than those recorded. Just reading through the time sheets I noted that a number of tasks I know were done during the week were never recorded.

Here’s how we spent our time:
Here are my thoughts on how we spent our time:
CityWalk—Our largest project took the largest portion of our time. That’s both good and expected.
Administration—This time was mostly answering the telephone on matters not related to an ongoing project. I think I need to hire someone to answer the telephone. Right now the system is only that whoever picks up the telephone first deals with it. Both the amount of time and number of interruptions are a problem. Not hiring a receptionist is probably penny wise and pound foolish.
Marketing/Fundraising—This is usually a significant number in nonprofits, but for us it’s even larger because I attend so many meetings (and skip even more that I probably should attend). This is mostly the time of Lori Beth Lemmon-Harrison, Director of Fundraising and Marketing, and me. Next time I’ll separate these two areas. The functions are related, but not the same—especially since we take a broad view of marketing.
Operating Properties—This time is mostly from Judy Lawrence, our property manager and seems about on target for our current operations. Right now we run three small apartment complexes, but when CityWalk opens and we have five times the number of units that we do now, I’m sure this category will require more time.
Government Relations—Johnice Woods handles this area. It takes up way more time than I like, but I don’t think I can do anything about it. There are rules and regulations, you know!
Neighborhood Stabilization Program—A big new initiative that will unroll this fall. We’re going to try to rebuild an entire low income neighborhood. Somehow, someway, we’re going to have to spend more time on this.
Review of New Projects—This time is mostly mine. Every week I look at a bunch of new ideas. Some of them originate with me, but a lot of them are brought to me to look at, sometimes by people we barely know. It’s like looking for a needle in a haystack, but sometimes you find one. All the projects we are doing started here.
The Cottages—This is another new project that I can’t even talk about yet. It’s going to need a lot more time over the next year.
Re:Vision Dallas—Yikes! Re:Vision Dallas will need bunches of more time as well.
Patriot Solar Power—Patriot Solar Power will get more time this week, and we have grant requests out to a number of organizations to fund this work.
People Against Drugs—A long story, but we’re temporarily caretakers for another nonprofit.
Cabana—A stalled project that won’t go forward until 2011 at best, but once in awhile we need to check back on it.
Central Dallas Ministries Resource Center—We’re helping CDM out a little by consulting on its efforts to build a new resource center.
Plaza—Proving that no good deed goes unpunished, once in a while something needs to be done to finish cleaning up this project, which failed last spring. Usually paying somebody’s bill.
Columbia—A pair of duplexes that we built and need to either sell or lease. I better make sure we spend a little more time making sure one of those things happens.
As you see, we’re working on a lot of projects, and a few are still missing here. Apparently we just didn’t get to them last week. Fortunately, there is always next week.
CityWalk—Our largest project took the largest portion of our time. That’s both good and expected.
Administration—This time was mostly answering the telephone on matters not related to an ongoing project. I think I need to hire someone to answer the telephone. Right now the system is only that whoever picks up the telephone first deals with it. Both the amount of time and number of interruptions are a problem. Not hiring a receptionist is probably penny wise and pound foolish.
Marketing/Fundraising—This is usually a significant number in nonprofits, but for us it’s even larger because I attend so many meetings (and skip even more that I probably should attend). This is mostly the time of Lori Beth Lemmon-Harrison, Director of Fundraising and Marketing, and me. Next time I’ll separate these two areas. The functions are related, but not the same—especially since we take a broad view of marketing.
Operating Properties—This time is mostly from Judy Lawrence, our property manager and seems about on target for our current operations. Right now we run three small apartment complexes, but when CityWalk opens and we have five times the number of units that we do now, I’m sure this category will require more time.
Government Relations—Johnice Woods handles this area. It takes up way more time than I like, but I don’t think I can do anything about it. There are rules and regulations, you know!
Neighborhood Stabilization Program—A big new initiative that will unroll this fall. We’re going to try to rebuild an entire low income neighborhood. Somehow, someway, we’re going to have to spend more time on this.
Review of New Projects—This time is mostly mine. Every week I look at a bunch of new ideas. Some of them originate with me, but a lot of them are brought to me to look at, sometimes by people we barely know. It’s like looking for a needle in a haystack, but sometimes you find one. All the projects we are doing started here.
The Cottages—This is another new project that I can’t even talk about yet. It’s going to need a lot more time over the next year.
Re:Vision Dallas—Yikes! Re:Vision Dallas will need bunches of more time as well.
Patriot Solar Power—Patriot Solar Power will get more time this week, and we have grant requests out to a number of organizations to fund this work.
People Against Drugs—A long story, but we’re temporarily caretakers for another nonprofit.
Cabana—A stalled project that won’t go forward until 2011 at best, but once in awhile we need to check back on it.
Central Dallas Ministries Resource Center—We’re helping CDM out a little by consulting on its efforts to build a new resource center.
Plaza—Proving that no good deed goes unpunished, once in a while something needs to be done to finish cleaning up this project, which failed last spring. Usually paying somebody’s bill.
Columbia—A pair of duplexes that we built and need to either sell or lease. I better make sure we spend a little more time making sure one of those things happens.
As you see, we’re working on a lot of projects, and a few are still missing here. Apparently we just didn’t get to them last week. Fortunately, there is always next week.
Subscribe to:
Posts (Atom)